Large scale inverter replacement supporting data centre cooling pumps.

icon image

The Challenge

110kW Inverter Replacement, Secondary Cooling Pumps

The site’s cooling pumps rely on a 110kW inverter to drive the Armstrong pump. Cooling is central to reducing reliance on mechanical chillers and the inverter driving the pump needed replacing without disruption. A job of this scale, at 110kW, sits at the top end of pump control equipment and demonstrates large scale data centre capability.

The Solution

  • Engineers attended site to isolate and safely remove the existing 110kW inverter from the Armstrong pump.
  • A replacement Danfoss FC202 110kW IP54 inverter was supplied and installed.
  • The existing back plate on the Armstrong motor was reused to mount the new inverter, avoiding unnecessary additional works.
  • All mechanical and electrical connections were completed, and the system was tested before being left fully operational.


outcome icon

The Outcome

Cooling capability was restored at full 110kW capacity, with the replacement completed cleanly using existing mounting infrastructure.

  • Cooling capacity fully reinstated, supporting the site’s energy-efficient cooling strategy.
  • Reuse of the existing back plate avoided unnecessary rework and kept the job efficient.
  • Demonstrates Dura Pump’s capability to handle high-power, industrial-scale inverter replacements as confidently as smaller routine works.


Choosing Dura Pump means investing in reliability and safety for your facility. Talk to an expert about your needs

We’ve had great reviews

Clear, Consistent Communication

The communication from Dura Pump to the customer is very good. We knew what was happening with the repair every step of the way

Purchasing Manager

Outstanding Turnaround

We just wanted to feedback our grateful thanks to Chris and Phil for all their hard work yesterday in getting us up and running again. To turn us around from failure to full recovery in 4/5 hrs was nothing short of exceptional. Please pass on our gratitude to them both.

Operations Manager

Seamless End-to-End Service

Service and communication received from initial inspection and specification through to delivery and installation of our replacement system was seamless. Thank you.

Facilities Supervisor

Informative & Helpful Engineers

Your engineers are always informative and always let me know when they are on site. Always very helpful, always kept well informed, which makes such a difference!

Building Manager

Fast, Friendly & Efficient

Fast, efficient, friendly staff in sales, accounts and installation. Very happy.

Project Coordinator

Top-Quality Workmanship

Over the moon with the service and quality of work/engineers.

Maintenance Manager